| Reference number | Lead project partner | Project title | Grant value | Techno group |
|---|
| 2002-8-26 | (Natural Environment Research Council) British Geological Survey | On-line temp prediction and site characterisation for UK Ground Source Heat Pump system design | £64,709.00 | Other |
| 064-139 | 4Energy Ltd | Low Carbon Cooling for Telecommunication Basestations | £199,162 | Buildings - Cooling |
| 2002-6-63 | Ambi-Rad | Improving the performance of radiant heaters by incorporating a second stage convective heat exchanger. | £50,114.00 | Demand side buildings |
| 2004-7-1561 | AquaEnergy Development UK Ltd | AquaBuoy - Hose-pump Optimisation | £168,000.00 | Supply - renewables |
| 075-048 | nano-porous Solutions Limited | Energy Saving, High Efficiency Compressed Air Treatment | £230,173 | Industry-specific Processes |
| 062-181 | Artemis Intelligent Power | Hydraulic transmission for large renewable generation devices including offshore wind | £244,055 | Wind – on- and off-shore |
| 2004-6-1408 | Artemis Intelligent Power Ltd | Efficient Hydraulic Motor for Marine Renewable Energy Device | £160,387.00 | Supply - renewables |
| 2005-3-2919 | AWS Ocean Energy Ltd | Design of a Prototype AWS Wave-Energy Generator | £125,000 | Supply- renewable |
| 2002-12-84 | BHR Group Ltd | Energy Efficient Kilns | £109,382.00 | Demand side industry |
| 063-068 | Building Research Establishment (BRE) Ltd | Low carbon calcium silfoaluminate cements - long term performance and industry coordination | £100,000 | Building Fabric |
| 2004-3-896 | Building Research Establishment (BRE) Ltd | Reducing CO2 emissions through the use of calcium sulfoaluminate based cements | £108,499.00 | Demand side industry |
| 2002-9-87 | Building Research Establishment Ltd | Energy savings potential of boiler controls | £44,850.00 | Demand side industry |
| 062-055 | Biomass CHP Ltd | Integration of modern gas engines into Biomasss CHP plants | £50,000 | Biomass for local electricity generation |
| 2002-9-61 | Birmingham City Council | Demo of CHP Tech | £51,943.00 | Supply - fossil / Conventional |
| 2003-9-245 | Bradford West City Community Housing Trust Ltd | Building integrated wind turbine demonstration | £79,830.00 | Demand side buildings |
| 2003-2-25 | Burnertech | Gas burner design project | £160,478.00 | Demand side industry |
| 2002-12-85 | Bristol electric Railbus | Zero emission hybrid railcar | £48,800.00 | Other |
| 2004-10-1979 | BSRIA | Biomimetic composites in building fabrics | £18,991.00 | Demand side buildings |
| 2003-11-203 | Camfridge Ltd | High-efficiency magnetic refrigeration | £198,808.00 | Demand side industry |
| 2003-9-95 | Carbon Disclosure Project | CDP II & III | £165,000.00 | Other |
| 2003-5-5 | Cardiff University | RESCOPE | £45,902.00 | Other |
| 064-003 | Cascade Technologies Limited | Development of a Prototype Combined C02 Flue Gas Capture and Measurement System | £196,772 | Carbon sequestration |
| 2002-7-28 | CCLRC | Building mounted wind turbines | £54,214.00 | Demand side buildings |
| 2002-11-21 | Ceres | IT-SOFC Electrolyte Manufacture | £193,000.00 | Supply - fossil / Conventional |
| 2003-3-81 | Ceres | Electrode dev for intermediate temperature SOFCs | £200,000.00 | Supply - fossil / Conventional |
| 064-130 | Ceres Power | Development and scale up of a low cost sintering process for metal supported SOFCs | £160,000 | Fuel cells - domestic CHP |
| 2005-3-2660 | Ceres Power Ltd | Electrolyte Process Development for MS-SOFCs | £200,000 | Supply – fossil/conventional |
| 2005-3-2855 | Clearpower Technology Ltd | WAVEBOB Tank Tests | £51,873 | Supply-renewable |
| 2002-12-17 | CMR Fuel Cells Ltd | Performance validation of a CMR fuel cell | £300,000.00 | Supply - fossil / Conventional |
| 2003-5-22 | Cosworth Technology | Controlled Auto-ignition | £199,722.00 | Demand side industry |
| 2002-12-69 | C-Tech | Prevention of icing on refrigeration coils | £59,030.00 | Demand side industry |
| 2002-6-231 | C-Tech Innovation Ltd | Enhancement of catalysis by a low energy electrochemical technique | £36,716.00 | Demand side industry |
| 051-319 | C-Wave | Innovative Wave-Energy Converter | £161,195 | Supply- renewable |
| 2002-9-79 | Department of Health | Specification to deliver Low Carbon Solutions in the NHS | £61,916.00 | Demand side buildings |
| 2003-8-124 | Direct Thrust / Trident | Direct energy conversion system | £73,686.00 | Supply - renewables |
| 075-204 | Doosan Babcock | Bioethanol production-reduction of fossil fuel utilisation | £113,827 | Biomass for Power |
| 2003-6-53 | DSL Processing | Prototype dev for commercial scale prod of ink grade carbon black from post pryolysis tyre char | £122,934.00 | Demand side industry |
| 2002-12-90 | E A Technical Services Ltd | Heat pump with integral expansion turbine | £143,028.00 | Demand side industry |
| 2002-9-36 | E A Technology Ltd | Retail Energy and Environment Club | £45,500.00 | Other |
| 2003-4-5 | Earthcare | The dev of low energy integrated commercial refrigeration technology | £69,743.00 | Demand side buildings |
| 2004-7-1665 | Enecsys Ltd | Next generation power conditioning units | £250,000.00 | Demand side industry |
| 062-178 | Edinburgh Uni | Electroreduction of CO2 to fuels and chemicals by innovative catalytic technology | £175,794 | Industry Alternative Equipment |
| 051-342 | Embley Energy | Advanced concrete structural design for SPERBUOY wave-energy converter | £150,000 | Wave – Offshore/nearshore |
| 077-104 | ENV-Aqua | Towards the eliminiation of process chemistry dragout loss | £249,579 | Industry - Process control |
| 062-079 | E-Stack Ltd | Natural ventilation of large open buildings using multiple E-Stacks | £75,000 | Demand - Buildings |
| 2002-12-52 | Filsol Solar | Development of an innovative mixed mode solar collector for household space and water heating | £51,634.00 | Supply - renewables |
| 2003-4-42 | Freepower | FP6 Demonstration Programme | £150,233.00 | Demand side industry |
| 2004-10-1872 | Glamorgan University | Hydrogen production from wheat industry co-product | £209,992.00 | Enabling technologies |
| 2003-3-82 | Glass Tech Services | Feasibility study of the balance between melting temperatures and waste glass in glass melting furnaces | £15,852.00 | Demand side industry |
| 2004-3-879 | Glass Technology Services Ltd | Reformulation of container glass composition | £192,019.00 | Demand side industry |
| 2002-6-32 | Glass Technology Services Ltd | Reformulation of Container Glass | £54,850.00 | Demand side industry |
| 062-108 | GlowLed Ltd | Significant Improvement of Glowled Experimental High Power LED Energy Saving Light Bulb | £225000 | Buildings - Lighting |
| 2003-3-44 | Greenfile Developments | Linking lean construction to the low-carbon economy | £27,000.00 | Demand side buildings |
| 2004-11-2243 | HeliSwirl Technologies Ltd | SMAHT Industrial Application Testing Programme | £100,000.00 | Demand side industry |
| 2003-3-110 | Heliodynamics | Suntrap thermal only low cost modules interfaced to drive a 10 tonne commercial chiller air-con system | £113,225.00 | Supply - renewables |
| 2002-6-139 | Heriot-Watt University | Low-cost modular proton-exchange membrane electrolysers: a feasibility study | £48,750.00 | Enabling technologies |
| 2003-12-296 | Hertfordshire County Council | Howe Dell school IHT demonstration | £244,325.00 | Demand side buildings |
| 2002-7-57 | HILTech Developments Ltd | Feasibility of developing novel high volume fuel cell hydrogen storage using thermally restructured d-developed PAN. | £47,160.00 | Enabling technologies |
| 2005-3-2931 | Horizon Ceramics | From Ice to Fire | £114,183 | Industry - process intensification |
| 063-105 | Howes-Macnaghten | Howes-Macnaghten Heat Pump | £250,000 | Buildings - Heating |
| 2002-12-7 | Hydro Venturi / Imperial | Third generation tidal stream device | £200,000.00 | Supply - renewables |
| 2002-12-35 | Hydrogen Solar | Photocatalyic conversion of sunlight to hydrogen using the Tandem Cell | £231,300.00 | Conventional |
| 064-133 | Ilika Technologies Ltd | High Throughput Synthesis and Screening of Platinum Free Electrocatalysts for Fuel Cell Applications | £167,000 | Fuel Cells - Transport |
| 064-179 | Imperial College | Optimisation of organic bulk heterojunction solar cells | £54,000 | Solar PV |
| 063-231 | ISKRA Wind Turbines | To enhance reliability and reduce cost of the ISKRA wind turbine through a novel pitch control system | £47,500 | Wind – on- and off-shore |
| 2002-9-49 | IT Power | Photovoltaic Installer Training | £74,730.00 | Supply - renewables |
| 2002-9-86 | IT Power | Training & accreditation of solar water heating systems | £86,227.00 | Supply - renewables |
| 2003-6-65 | IT Power | Fish Friendly turbines | £81,993.00 | Supply - renewables |
| 2005-3-2835 | Joules Energy Efficiency Services Ltd | TETRON Wave Energy Device | £128,300 | Supply -renewable |
| 2005-2-2424 | JTL Systems Ltd | AVID INCISER, Defrost on Demand System | £48,296 | Demand side industry |
| 2005-6-3203-7 | Keld Energy Ltd | Novel, high-efficiency biomass CHP system | £150,000 | Waste to Energy |
| 2002-9-101 | London Borough of Croydon | Woodchip from waste for renewable heat and power | £61,752.00 | Supply - renewables |
| 2003-3-120 | London South Bank University | A novel low carbon superconductive food display cabinet | £36,934.00 | Demand side industry |
| 2004-7-1527 | London South Bank University | Sustainable Cooling Systems | £70,461.00 | Demand side buildings |
| 2003-2-35 | Leeds University | Energy efficient injection mould tooling | £151,408.00 | Demand side industry |
| 2002-12-22 | Loughborough University | Dev of a highly effective and very low energy space cooling system for buildings | £170,133.00 | Demand side buildings |
| 2002-9-83 | Loughborough University | Training for new and renewable energy in the built environment | £91,238.00 | Other |
| 062-120 | Lontra Ltd | Energy efficient prototype compressor | £170,250 | Industry -Alternative |
| 064-204 | Matthews Pallandt Consultancy Services Ltd | 1.1 Floating Wind Turbines | £250,000 | Offshore Wind |
| 051-109 | Microsharp Corporation Ltd | Optical Film for Ultra-Low-Cost Solar Concentrators | £176,372 | Supply- renewable |
| 2003-5-41 | Norman Hay Plc | Low energy water purification units | £73,190.00 | Demand side industry |
| 2002-6-66 | Oakdene Hollins Ltd | Transforming energetics of base metal and alloy processes | £45,150.00 | Demand side industry |
| 2002-12-46 | Ocean Wavemaster | Harnessing ocean waves to generate electricity | £161,550.00 | Supply - renewables |
| 2003-3-122 | Offshore Wave Energy Ltd | The OWEL Wave Energy Converter | £160,000.00 | Supply - renewables |
| 2003-12-284 | Orecon Ltd | Industrial Development of the "MRC" wave-powered generation system | £134,534.00 | Supply - renewables |
| 2004-7-1530 | Oxford Catalysts | Improved reformers for fuel cells | £150,000 | Fuel cells – Industrial & Commercial |
| 2004-2-642 | PCA Engineers Ltd | CO2 reduction through better fan / heat exchanger design | £98,599.00 | Demand side industry |
| 2004-11-2078 | Perkins Engines Company Ltd | Linking Diesel Engine Research with Next-Generation Biofuels | £181,851.00 | Demand side industry |
| 2003-11-110 | Plymouth University | In-situ measurement of the thermal properties of building materials | £97,275.00 | Demand side buildings |
| 076-162 | Pure Marine Glen | DUO WEC: multi-mode wave energy device | £153,522 | Wave offshore |
| 2002-6-255 | Portico Software Ltd | Proof of concept of an energy analysis and monitoring tool | £173,579.00 | Enabling technologies |
| 076-135 | Power Oasis | Project PowerOasis | £125,000 | Grid connection and balance of system |
| 076-213 | Queen's University Belfast | Exploiting low grade methane for greenhouse gas reductions and renewable power production | £101,500 | Small scale CHP |
| 2003-4-36 | Rocktron Ltd | PFA Process and consequent cement substitution with subsequent CO2 reduction | £160,000.00 | Demand side industry |
| 2002-7-100 | Schneider Electric Ltd | Managed Energy Transformer | £100,000.00 | Demand side industry |
| 2002-9-85 | Society of British Gas Industries | Demand Analysis Model | £43,000.00 | Supply - fossil / Conventional |
| 2005-7-3390 | Scotrenewables Ltd | Marine Power Cost-of-Energy Analysis | £149,978 | Supply- renewable |
| 2002-9-30 | Scottish Energy Environment Foundation | (RESPIRE) Renewable energy sources promotion and integration in insular regions of Europe | £85,468.00 | Enabling technologies |
| 2002-8-89 | Shropshire County Council | Heat pumps in rural off gas grid buildings | £42,000.00 | Demand side buildings |
| 2003-2-32 | Silsoe Research Institute | Localised air delivery to reduce energy use in the food industry | £78,270.00 | Demand side industry |
| 051-194 | Spirax Sarco Ltd | Development of a Steam Trap Acoustic Sensor | £150,000 | Industry – process control |
| 2003-3-70 | Solar Century | R&D of roof integrated solar solutions | £76,281.00 | Supply - renewables |
| 076-133 | Sustainable Energy Ltd. | Development and Implementation of an Effluent Clean-Up System for Biomass Gasification CHP System | £60,537 | Biomass for Electricity |
| 051-382 | St Andrews Fuel Cells Ltd | Optimising solid oxide fuel cell bundles for efficient power generation | £203,560 | Fuel cells – industrial & commercial |
| 2003-6-3 | Southside Thermal Sciences Ltd | Sensor Coatings (SATURN) | £214,322.00 | Demand side industry |
| 2003-11-232 | Swansea University | Injection moulding process intensification | £103,993.00 | Demand side industry |
| 2005-6-3250 | Technology Innovation Centre | Biofuel Production for Local Power | £177,633 | Supply- renewable |
| 2004-10-1813 | Telensa | Energy saving in street lighting | £250,000.00 | Demand side buildings |
| 2003-2-46 | The Association for the Conservation of Energy | Asset value implications of low energy offices | £24,938.00 | Demand side buildings |
| 2002-9-80 | The Chartered Institution of Building Service Engineers | Low Carbon Building Services Toolkit | £16,300.00 | Demand side buildings |
| 2002-7-173 | The European Marine Energy Centre | Orkney Marine Energy Test Centre | £1,195,000.00 | Supply - renewables |
| 2004-7-1582 | The Martin Centre University of Cambridge | A Low Energy Whole House Ventilation System | £148,501.00 | Demand side buildings |
| 076-124 | Thermofluidics Ltd | Low temperature-difference pumping-engines without moving parts | £175,000 | Industry general equipment |
| 076-068 | United Utilities | Low carbon sewage treatment | £109,686 | Industry-specific processes |
| 051-233 | University of Aberdeen | Demonstration of a Dynamic, Breathing Building | £250,000 | Demand side buildings |
| 2002-6-191 | University of Birmingham | Bio-fuels for clean and efficient engines: enabling controlled auto ignition combustion technology by fuel reforming. | £63,945.00 | Other |
| 2002-6-263 | University of Birmingham | The safe efficient and economic large scale storage of hydrogen | £128,400.00 | Enabling technologies |
| 2003-6-7 | University of Cambridge | A demo plant for intensified continuous production of biodiesel using the oscillatory flow reactor | £75,000.00 | Other |
| 2003-6-49 | University of Cambridge | Fuel Cell Off Gas Combustor | £129,037.00 | Supply - fossil / Conventional |
| 2005-3-2723 | University of Coventry | Reduction of Energy Consumption in Aluminium Smelting | £150,000 | Industrial Research |
| 2002-7-39 | University of Glamorgan | Feasibility of Sustainable Hydrogen Production from Starch Industry co-products | £64,850.00 | Enabling technologies |
| 2004-6-1330 | University of Glamorgan | Development of New Combustion Configuration for Primary Glass Melting | £250,000.00 | Demand side industry |
| 2002-6-8 | University of Glamorgan | Feasibility of Firing Primary Glass Melting for Reduction of CO2 Emissions | £61,964.00 | Demand side industry |
| 2004-3-809 | University of Glamorgan | Optimisation of biomass combustion on chain grates | £98,925.00 | Supply - renewables |
| 2003-6-57 | University of Leeds | A novel inert alloy electrodes for aluminium smelting | £99,870.00 | Demand side industry |
| 2002-7-123 | University of Leicester | Self optimising ventilation systems incorporating new low cost high efficiency electronically controlled motors | £144,344.00 | Demand side buildings |
| 076-207 | University of Liverpool | Laser-Ignition for Automotive and Bio-Fuel Engines | £150,000 | Improved road vehicles |
| 2004-2-658 | University of Liverpool | High voltage current interruption without SF6 | £246,849.00 | Demand side industry |
| 2004-10-1867 | University of Manchester | The Manchester Bobber | £52,125.00 | Supply - renewables |
| 2002-12-75 | University of Newcastle | Direct alcohol fuel cell | £81,312.00 | Supply - fossil / Conventional |
| 2002-12-34 | University of Newcastle | Capillary fuel Cell | £157,880.00 | Supply - fossil / Conventional |
| 2002-7-83 | University of Nottingham | Heat recovery system using sorption dehumidification of natural gas exhaust | £39,945.00 | Demand side industry |
| 2002-6-38 | University of Nottingham | Developing effective absorbent technology for the capture of CO2 in fossil fuel-fired power plant | £180,392.00 | Supply - fossil / Conventional |
| 2002-6-96 | University of Sheffield | Directed Evolution for Bioprocess Intensified Low-Carbon Bio fuels Generation | £51,248.00 | Enabling technologies |
| 2003-3-51 | University of Sheffield | Low cost energy efficient compressors for refrigeration | £197,258.00 | Demand side industry |
| 051-322 | University of Surrey | Ultra Low energy high brightness lighting | £200,000 | Buildings - Lighting |
| 2002-12-109 | University of St Andrews | Implementation of 2nd generation SOFC anodes | £162,737.00 | Supply - fossil / Conventional |
| 2003-8-5154 | University of Southampton | High-efficiency low cost photosensitised solar cell | £180,000.00 | Supply - renewables |
| 2002-12-27 | University of Warwick | Radiant recuperative burner for industrial furnaces using permeable ceramic membranes | £71,221.00 | Demand side industry |
| 2003-8-1041 | UMIST | Robust point wave energy device with smooth output | £39,770.00 | Supply - renewables |
| 2004-11-2035 | Viridian concepts Ltd | Building integrated solar hot water systems | £213,608.00 | Supply - renewables |
| 2003-3-10 | W K McMillan Steel Fabricators | Industrial development of a building integrated ducted wind turbine module | £21,750.00 | Demand side buildings |
| 051-325 | Warwick Manufacturing Group | Eliminate Paint Shops | £250,000 | Industry - process intensification |
| 2003-3-86 | Warwick Ventures | Dev of prototype for convective thermal wave absorption technology | £199,373.00 | Demand side buildings |
| 2003-6-12 | Waveplane | Waveplane R&D project | £268,151.00 | Supply - renewables |